Teesport Berth 1 Phase 2, Middlesbrough

Teesport Berth 1 Phase 2, Middlesbrough Teesport berth 1 involved the demolition of an existing concrete deck structure and construction of a new suspended jetty.

Econ were contracted to carry out the installation of the port concrete pavements, crane rail installation, associated drainage (including installation of oil interceptors) and utility works.

Challenges encountered were the sequencing of the works including co-ordinating with Teesport Port Operations.

 

Client

McL&H/PD Ports

Value

12,000,000

Duration

40 weeks

Employers Representative

Royal Haskoning